Solved! Go to Solution.
Views
Replies
Total Likes
Hi @SamuelSh3
To your second question first: In WF reporting you can only ever modify attributes of the business object on which the report is based. If it's a task report - you cannot modify project attributes and vice versa.
If the %complete is inadequate try a Milestone View on a project report. You cannot modify the % complete on these if they have subtasks and are set to auto-complete. But the view should give you an adequate sense of project progress AND you can click through to the Milestone tasks or project.
Hi @SamuelSh3
To your second question first: In WF reporting you can only ever modify attributes of the business object on which the report is based. If it's a task report - you cannot modify project attributes and vice versa.
If the %complete is inadequate try a Milestone View on a project report. You cannot modify the % complete on these if they have subtasks and are set to auto-complete. But the view should give you an adequate sense of project progress AND you can click through to the Milestone tasks or project.
@SamuelSh3 Just checking in — were you able to resolve your issue? We’d love to hear how things worked out. If the suggestions above helped, marking a response as correct can guide others with similar questions. And if you found another solution, feel free to share it — your insights could really benefit the community. Thanks again for being part of the conversation!
Views
Replies
Total Likes
Views
Likes
Replies