Expand my Community achievements bar.

The Community Ideas review for H1 2025 is out now, see which ideas our Product team prioritized and let us know your thoughts.

Update custom form based on tasks completed

Avatar

Level 1
We have a custom form that feeds a report for our stakeholders to know the status of the project. The % complete is not a clear indicator of the phase of our work/the project. Right now updating the status field in the form is manual and not tied to anything. We want to select specific tasks (mile makers) to be tied to the custom for to update the "status" field as they are completed. Is this possible? Alternatively, is there a way to add the "status" field as a column that can be viewed AND updated in the project view? So then, as we complete the mile marker tasks we can also update the status? I was able to add it as a column but am not able to edit while marking a task as complete. Thanks!
1 Reply

Avatar

Community Advisor

Hi @SamuelSh3 

To your second question first: In WF reporting you can only ever modify attributes of the business object on which the report is based. If it's a task report - you cannot modify project attributes and vice versa. 

 

SveniX_0-1750954817668.png

If the %complete is inadequate try a Milestone View on a project report. You cannot modify the % complete on these if they have subtasks and are set to auto-complete. But the view should give you an adequate sense of project progress AND you can click through to the Milestone tasks or project.