The first part of the information displays predecessor project details such as the Project Planned Start Date, Project Planned Completion Date, Project Condition and Project Status etc.
The second part focuses on predecessor task details. In your case task (#1):
1) The predecessor task (#1) is scheduled to start on July 14.
2) There seems to be an error in the end date, which needs to be addressed.
3) Predecessors 2 Tasks: 1216700:8ff and 884726:7ff
4) Successors 2 Tasks: Task #2 and Task #3 on the same project