Has anyone successfully been able to report on current days in process for a project? I'm basically looking to show how many days a project has been in process from the start date. Seems simple, but I've been told that there isn't a way to do this!
Super simple. I would just do a calculated field in a custom form. You'll need to make sure that custom form is applied to the projects you want to see this on.
You can change the entry date to the actual start date easily. Just replace 'Entry Date' with 'Actual Start Date'
We use entry date because we don't always have a good grasp on when ur projects are actually started, but they're in our court as son as they're entered.