Has anyone had tasks that do not show up on a timesheet unless you open it and save?
I have some tasks set monthly for projects. I could have a task for September for Mary Doe and a task for October for Mary Doe. For some reason, the task doesn't always show on the timesheet for a month. If I go in and change it from "New" to "In Process", it will normally then appear on the timesheet. If it is already set to "In process", I change the individuals role and then it will appear on the timesheet. Any insight on what I might be missing so I don't need to do manual intervention?