Hi Michael. Welcome to Workfront. What's the relationship between the two tasks? Is the first one the predecessor of the second? There is an attribute of the task called 'Ready' that you can filter on to show true - that is all tasks that don't have any unfinished predecessors. Or, you could filter on the parent tasks status - the parent task being the task it is indented under. Or you could filter on predecessors status. You should probably use the last one as a last resort - if you filter on the predecessors being closed, you're effectively checking the 'Ready' status but because they can be multiple predecessors it's a more complex area in reporting.
Barry Buchanan - WMA Work Management Australia