Views
Replies
Total Likes
Views
Replies
Total Likes
Views
Replies
Total Likes
Hi all - thanks for your response. This is what I am getting - I made the task name the use case What I was hoping for was I put in the planned start and end dates, it calcs the hours/duration and then I change the allocation of that resource on the task and it changes the hours to that John Hoebler Cross Country Consulting
Views
Replies
Total Likes
Hello, I am a new customer needing to do exactly what you described in this post. Did you find a way to accomplish this? I need to set the Task Constraints to Fixed Dates so that I can enter the Planned Start and Planned End Dates. I set the Duration Type to Calculated Work so that I could assign one or more workers and define the % allocation for each to something less than 100% for each. When I first created the task, I assigned it to a team and was able to set the Planned Start and Planned End Dates. Once I assigned the task to workers within the team and assigned % allocation, the Planned Start and Planned End Date fields were hidden. It appears I can still change the Planned End Date but there is no way to get back to the Planned Start Date, which I might want to do if the task gets delayed and gets a new start date. Any thoughts you can share from your experience would be helpful.
Views
Replies
Total Likes
UPDATE: I learned through customer support that the reason the Planned Start and End Dates were disappearing when I assigned the task was because the task had originally been created by me (considered a PERSONAL task) and then was assigned to a team (now considered a NORMAL task) and then assigned back to me (switching it back to a PERSONAL task). KEY NOTE: These tasks are not project tasks; they are request tasks originating from the Work List view.
Views
Replies
Total Likes
Views
Replies
Total Likes
Views
Replies
Total Likes
Views
Likes
Replies
Views
Likes
Replies
Views
Likes
Replies