Default Planned Completion Date on Request

Avatar

Level 5

Is there a way to set a default planned completion date when a request is submitted rather than manually adjusting? For example, we have a certain type of request that we'd like the Planned Completion Date to be set to submission date + 3 days.

Any help is appreciated. Thank you!

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Level 8

In the queue details of your request queue, you can set a default duration for all of the requests that come in. If you set it to 3 all the requests planned completion dates will automatically calculate to be +3 days from the entry date of the request.

See here under 'Default Duration' a little more than halfway down the page: https://one.workfront.com/s/document-item?bundleId=the-new-workfront-experience&topicId=Content%2FMa...

View solution in original post

2 Replies

Avatar

Correct answer by
Level 8

In the queue details of your request queue, you can set a default duration for all of the requests that come in. If you set it to 3 all the requests planned completion dates will automatically calculate to be +3 days from the entry date of the request.

See here under 'Default Duration' a little more than halfway down the page: https://one.workfront.com/s/document-item?bundleId=the-new-workfront-experience&topicId=Content%2FMa...

Avatar

Level 5

Thank you SO much!! Exactly what I was looking for :)