Customizing Layout Templates - Task View on the Home screen

Avatar

Level 3

I see it is possible to display custom data from a Company custom form when viewing a Project in the Home screen but I do not see custom data from a Company Custom form as an option when viewing Tasks. I would like to be able to display company level information on a task. Is this possible?

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Reply

Avatar

Community Advisor

If it's one too many "hops" away you may need to bring the company info into the task by using a calculated field in maybe the project form to express the data and then call that field in Home.