Expand my Community achievements bar.

Join us LIVE in San Francisco on November 14th for Experience Makers The Skill Exchange. Don't miss out on this free learning event!
SOLVED

Custom field that stamps a value from another field

Avatar

Level 10

Hi WF Community,

Does anyone know of a way to create a custom field on the Task object that will do the following?

  • Capture the Planned Completion Date value in this new field, and don't overwrite this value if the Planned Completion Date field value is updated after its initial value.

I know how to create this field and have it capture the value from the Planned Completion Date field, but it overwrites the originally-captured-value once the Planned Completion Date field value is updated.

Thanks,

Nick

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Level 10

Oh, that is my bad... here you go!

IF(ISBLANK(Original Planned Completion Date),Planned Completion Date,Original Planned Completion Date)

View solution in original post

8 Replies

Avatar

Level 10

Hi,

I'll give you the formula, but you might want to use the baseline to capture this info so you get all info (planned start and completion date, as well as hours). In your setup, you can have your in your project preference an option checked that captures a baseline automatically when you convert the project from Planning to Current the first time. This allows your PM to adjust planned dates from templates and kick off meetings, but lock the info in place once the project is Current.

With my formula, the first time the custom field is attached to the task, it will capture the planned completion date and cannot be updated.

First, create field with blank formula and save. (I'm going to call it "Original Planned Completion Date"). After you save, go back in and put this formula:

IF(ISBLANK(Original Planned Completion Date),$$NOW,Original Completion Date)

Hope that helps.

Avatar

Level 10

Thanks, Anthony.

I forgot the obvious choice of Baselines - and yup, we have this enabled on project settings (Status moves to Current). However, I find the Baseline Tasks report a little limiting with regard to what fields you can use in prompts, as well as groupings and views. However, we might be able to work around that.

As for your formula, what object are you calling "Original Completion Date" from? The system is not recognizing that as a valid field in my calculation. I am using a Task custom form.

Avatar

Level 10

You should be able to use Default Baseline Task for a lot of your reporting. Planned hours, start dates, end dates, etc.

As for the calculation, did you do the first step? Create the field, leave the calculation blank, and Save? You need to do that first so that the field is created. Then you can go back in and put the calculation in.

Avatar

Level 10

Yup, I did that (saved without the calculation). It's just not recognizing the "Original Completion Date" as a legit field in the latter portion of the formula. I checked the API Explorer and couldn't find it.

Avatar

Level 10

It is the custom field. Here is how it looks to me in my instance

0694X00000J1QIwQAN.png

Is maybe the format not set to Date?

Avatar

Level 10

Thanks for the screenshot. I see where the confusion was now.

Hmmm, doesn't look like this formula will work. It's just grabbing today's date/time ($$NOW), and not taking the value in the Planned Completion Date field.

Avatar

Correct answer by
Level 10

Oh, that is my bad... here you go!

IF(ISBLANK(Original Planned Completion Date),Planned Completion Date,Original Planned Completion Date)

Avatar

Level 10

That's the chicken dinner!

Thanks, Anthony.