Level 1
Level 2
Melden Sie sich an, um alle Badges zu sehen
I created a New Template and my template durations are not rolling up correctly. I have task constraint set to 'As Soon as Possible'. See attached. I can't figure out why the durations do not roll up to total duration. I have tried everything.
Anhand von Themen werden Community-Inhalte kategorisiert und Sie können so relevanten Inhalt besser finden.
Zugriffe
Antworten
Likes gesamt
I don't see that you've attached anything so feel free to try that part again.
Zugriffe
Antworten
Likes gesamt
Hi Skyehansen, thank you for bringing this to my attention I have attached the screenshot.
Zugriffe
Antworten
Likes gesamt
Zugriffe
Antworten
Likes gesamt
Can you expand to show all 26 tasks? My feeling is that they aren't adding up because you don't have ENOUGH predecessors linking tasks from one end of the project to the other. By seeing all 26, we can maybe recommend some tasks that you can link to show the continuity of the project timeline.