I created a New Template and my template durations are not rolling up correctly. I have task constraint set to 'As Soon as Possible'. See attached. I can't figure out why the durations do not roll up to total duration. I have tried everything.
Topics help categorize Community content and increase your ability to discover relevant content.
Views
Replies
Total Likes
I don't see that you've attached anything so feel free to try that part again.
Views
Replies
Total Likes
Hi Skyehansen, thank you for bringing this to my attention I have attached the screenshot.
Views
Replies
Total Likes
Views
Replies
Total Likes
Can you expand to show all 26 tasks? My feeling is that they aren't adding up because you don't have ENOUGH predecessors linking tasks from one end of the project to the other. By seeing all 26, we can maybe recommend some tasks that you can link to show the continuity of the project timeline.