Creating a Template- Duration does not roll up to Parent task from Child Task

Avatar

Level 1

I created a New Template and my template durations are not rolling up correctly. I have task constraint set to 'As Soon as Possible'. See attached. I can't figure out why the durations do not roll up to total duration. I have tried everything. 

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

4 Replies

Avatar

Community Advisor

I don't see that you've attached anything so feel free to try that part again.

Avatar

Level 1

Hi Skyehansen, thank you for bringing this to my attention I have attached the screenshot. 

Avatar

Level 1

Screenshot 2025-09-03 at 5.49.30 PM.png

Avatar

Community Advisor

Can you expand to show all 26 tasks? My feeling is that they aren't adding up because you don't have ENOUGH predecessors linking tasks from one end of the project to the other. By seeing all 26, we can maybe recommend some tasks that you can link to show the continuity of the project timeline.