Expand my Community achievements bar.

Don’t miss the Workfront AMA: System Smarts & Strategic Starts! Ask your questions about keeping Workfront running smoothly, planning enhancements, reporting, or adoption, and get practical insights from Adobe experts.

Mark Solution

This conversation has been locked due to inactivity. Please create a new post.

Cost of user per week

Avatar

Level 1

I need to send a weekly report to upper management of the cost of each freelancer per week based on the hours that they logged. I assigned an hourly cost to each user and built a report that pulls in the time they logged at the task level and multiplies that time by their hourly cost. The issue I'm bumping into is that I have to manually click into all the tasks in each project template and update the "Cost Type" from "Role Hourly" to "User Hourly". If there is a simpler way to set the default to "User Hourly" or a different report that yields the same result please let me know. Thanks!

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

0 Replies