Calculated Fields List

Avatar

Level 2
Is there a list of the calculated fields in workfront and what each one calculates? I am trying to see if I can do a calculated field that will generate an automatic number i.e. 2019812, 2019813, 2019814, etc... Thank you, Trish Patricia Cowles
2 Replies

Avatar

Level 8
There isn't a 'counter' field type in Workfront, but every object has a unique Reference Number as well as an ID. The ID is hexadecimal, while the reference number is just an incrementing integer. Note that you won't get consecutive reference numbers for a single object type though - If I created a project with reference number 100 from a template with 10 tasks, the tasks will be numbered 101 - 110 so the next project I create would be 111. Barry Buchanan - WMA Work Management Australia