Calculated Assignment Duration Type - What Does the % Represent?

Avatar

Level 10

Hi WF Community,

I'm trying to determine what the assignment allocation % on a task means for a given assignee when we use the Duration Type 'Calculated Assignment'.

Is it a percentage of the project as a whole, or is it based off of a bunch of other stuff (e.g. the total hours assigned to an assignee for all of their work)?

Thanks.

Nick

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Level 10

Found the answer (thanks, Support):

Allocation percentage represents the amount of time an assigned resource is planned to work on a task in a day. It is the percent of a work day (according to the user or project schedule) at which a resource is allocated throughout the duration of the task. You cannot modify the percentage allocation of a resource assigned to an issue.

View solution in original post

1 Reply

Avatar

Correct answer by
Level 10

Found the answer (thanks, Support):

Allocation percentage represents the amount of time an assigned resource is planned to work on a task in a day. It is the percent of a work day (according to the user or project schedule) at which a resource is allocated throughout the duration of the task. You cannot modify the percentage allocation of a resource assigned to an issue.