I'm trying to determine what the assignment allocation % on a task means for a given assignee when we use the Duration Type 'Calculated Assignment'.
Is it a percentage of the project as a whole, or is it based off of a bunch of other stuff (e.g. the total hours assigned to an assignee for all of their work)?
Thanks.
Nick
Solved! Go to Solution.
Topics help categorize Community content and increase your ability to discover relevant content.
Found the answer (thanks, Support):
Allocation percentage represents the amount of time an assigned resource is planned to work on a task in a day. It is the percent of a work day (according to the user or project schedule) at which a resource is allocated throughout the duration of the task. You cannot modify the percentage allocation of a resource assigned to an issue.
Views
Replies
Total Likes
Found the answer (thanks, Support):
Allocation percentage represents the amount of time an assigned resource is planned to work on a task in a day. It is the percent of a work day (according to the user or project schedule) at which a resource is allocated throughout the duration of the task. You cannot modify the percentage allocation of a resource assigned to an issue.