Expand my Community achievements bar.

Bubble chart for project prioritization

Avatar

Level 5
I am trying to work out project priority decision chart. One thought is to map project value against risk, with the bubble representing project size (hours). Have all I need except that when I select RISK as an axis, the only option I get is SUM. That isn’t so useful, as all projects end up line up together. In the case shown in the attached, the parking project has a risk of LOW while the other is VERY LOW. I would expect to be able to graph these. Does anyone out here have thoughts on how to get this type of chart? What other portfolio decision charts are you using?
3 Replies

Avatar

Level 10
Marty, We've created a custom form that generates a score based on the answers to the questions within it, including scores for info we pull out of the business case, etc. That score gives us a general idea of which projects we should consider and from there we have a dashboard similar to the Portfolio Optimizer that shows the Portfolio Budget, how the projects are doing on schedule and budget, etc. (However, it takes actual and EAC into account.) It also shows all of the projects in the portfolio, filtered via various reports into groupings that make sense. The projects have a custom field (In/Out) showing in the report that we can update from the dashboard. Projects that are in are factored into the Portfolio Budget/Actual chart, schedule charts, budget charts, etc. Projects that are out aren't factored in. It's clunky and ugly but it let's us make reasonably informed decisions.

Avatar

Community Advisor
Hi Marty, I find Bubble Charts one of the most powerful and difficult reports to work with. I think the main trick is to create dispersion, in order to separate what's being compared into different quadrants. To do that, each item needs some mechanism to give it both a variable value on the Y and X axis. As an example, here is a video showing a Bubble Chart that I developed for monitoring Issues. The Bubble sizes are driven by the number of Planned Hours it will take to solve the Issue. The Bubble colors are the Priority of each Issue, which is excellent for "toggling". The X axis is the number of days early until (positive) or late (negative) each issue is, relative to its due date (zero). The Y axis is a calculation of the importance of the Issue, which is primarily driven off the priority of the issue, but also takes the Issue's due date into mind: the further away it is, the lower that importance (in fact, decreasing to zero 90 days out, meaning "too far out to worry about yet"), and then gradually "floating" higher as the due date approaches, peaking at a known amount "on" the due date (which varies by priority; e.g. Urgent = 100000, High = 80000, Normal = 50000, Low = 30000). Once it's late, the slope of the float INCREASES for Urgent/High/Normal items, but DECREASES for Low items, the latter sinking into the backlog. In this manner, the priority of what to work on becomes obvious: using the axis to divide the work into quadrants, the top left is high priority and late, top right is important, with the left side being due soonest, and the bottom left is least important (the backlog). Once items start "bumping" against the far right (arbitrary) wall -- 90 days late, in my example -- it's time to get real: these one's are NOT getting done, so either reset the due date into the future, or kill them. And finally, as per the video, the prompts on the chart for priority, height, and time frame effectively allow users to "zoom in" on whatever is of interest to them (e.g. "show only Urgent in the top left quadrant"). In fact, I set up a dashboard that opens (by default) to show everything in a chart at the top, and then six "zoomed in" charts, like this, allowing quick triage of what's going on: ---BIG CHART -- --------top left-------- ------top middle----- -------top right------- ------bottom left----- ---bottom middle--- ----bottom right---- Incidentally, I got this idea for this from the coolest Bubble Chart I've ever seen and someday, intend to animate my Workfront bubble charts in a similar manner. So! With that primer in hand, back to your original question about Project Prioritization. As part of JITR , we use a concept called Project Priority Indicator, which effectively forces the vertical distribution (bubble chart-wise) of every Project. It can be a simple manually entered numeric ordinal, or a complex formula that uses custom data drivers, portfolio weights, and/or portfolio optimizer rankings: the point is, every Project's importance will vary: that's the Y axis (noting that Project "value" is also an excellent standalone, less contentious candidate). The X axis can then be time based -- e.g. Planned Completion date, similar to my Issue example -- but could also be in number of days (e.g. "days until decision date" is a good one for sales based projects); but using something like a confidence level (thinking of classic sales funnels) also makes a good option. The size of each bubble could be value, or cost, or hours, or some calculated field, and the color (I've come to learn) works best with out of the box fields such as priority (which have standard colors), since although you can use a calculated field in a grouping for the colors, they can quickly exceed the relatively low limit, and the chart will refuse to render with a "Woah..." message. Thanks for raising such an interesting question: I've been meaning to blog about this for ages, and think this pretty much covers what I had in mind! Regards, Doug

Reinstating a link to the missing BubbleChart.mp4 file (although the reformatting the previous post will have to wait).

 

Regards,

Doug

 

https://atappstore.com/Extras/BubbleChart.mp4

Doug_Den_Hoed__AtAppStore_0-1688578948626.png