Expand my Community achievements bar.

Boards Question - Adding new tasks to the backlog automatically from a linked project

Avatar

Level 5

When using the new Boards feature I can use the Add card button to add connected cards. This allows me to select a project and the relevant tasks. Is there a way for this to be setup so that any new tasks automatically can be pulled into a backlog column? 

 

We've had some users show interest in the new Boards, but I'd need that to function before I'd be able to get buy-in. 

1 Reply

Avatar

Community Advisor

Hi there, you can set up an intake column on your board to pull in objects to potentially become cards in your boards. More on that here: https://experienceleague.adobe.com/docs/workfront/using/agile/agile-planning-boards/add-intake-colum... 
You can set up your columns to work with your cards based on a few things like status, tags, etc. More on that here: https://experienceleague.adobe.com/docs/workfront/using/agile/boards-in-workfront/manage-board-colum... 
If you found this helpful, please mark correct to help others : )

If this helped you, please mark correct to help others : )