Assignments report - Multiple users are assigned to a task - Removing task from assignment report for the user with their part of a task 'complete'

Avatar

Level 2

Assignments report - when multiple users are assigned to a task, and an assignments report is used to highlight all tasks associated to a user.

Why, then is a task not removed from the assignee that has completed their part of a task. I can't understand how to remove these tasks from the report.

주제

토픽은 커뮤니티 콘텐츠를 분류하여 관련성 있는 콘텐츠를 찾는 데 도움이 됩니다.

2 답변 개

Avatar

Level 10

Hi Charlotte - just to make sure, do you have a filter for Assignment Status? Each assignment has a status (Request, Working, Done) that is different from the task or issue status. This means you will need to add Assignment >> Status does not equal Done if you want to remove line items from the Assignment report when someone clicks "Done With My Part"

Hope that helps 🙂

Avatar

Level 3

Perfect!  I conducted research to determine if this was feasible and was unable to find the suitable answer. This is exactly what I needed!!