Expand my Community achievements bar.

The next phase for Workfront Community ideas is coming soon. Learn all about it in our blog!

assigned, but not accepted, tasks

Avatar

Level 1
Looking for a way to report on tasks that have been assigned but the assignee has not accepted (not clicked "work on it") the task Jessie Yull
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

2 Replies

Avatar

Level 10

Hi Jessie, When doing a task report, you can add the column Assignment and Status and that will tell you who hasn't accepted as well as who is done with their part. We use it for our PMs on their report widget, Tasks Due This Week. That way if they see Requested still they know they will need to follow up as the person might not even know they are supposed to do it. Our PMs like this. Anthony Imgrund FCB0690z000007ZiTdAAK.png

Avatar

Level 10
Hi Jesse, In addition to Anthony's tip, I suggest you filter for Tasks whose AssignedToID is not null (therefore Assigned), and whose Handoff Date is not null (therefore Ready To Be Worked On), and whos Commit Date is null (therefore No One has committed to Work On It), as this trifecta will then focus on the data of most concern. Regards, Doug Doug Den Hoed - AtAppStore