Expand my Community achievements bar.

Join us LIVE in San Francisco on November 14th for Experience Makers The Skill Exchange. Don't miss out on this free learning event!
SOLVED

Ask for help: How can set holidays in Work Front Timeline, so that tasks can be avoided to complete in this timeframe

Avatar

Level 3

Hello Friends,

I have a question, in Microsoft Project software, I can set the project calendar excluding the holidays, so the tasks will not be fell into this timeframe,

but in Workfront, how can I set this calendar? or by other methods of setting holiday tasks? Please help advise. Thanks!

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Level 3

@JerryWu 

Go to the project settings and you'll see 'User Time Off'. There's a couple of options, either 'Consider' or 'Ignore'.

Project Settings 2.png

View solution in original post

5 Replies

Avatar

Correct answer by
Level 3

@JerryWu 

Go to the project settings and you'll see 'User Time Off'. There's a couple of options, either 'Consider' or 'Ignore'.

Project Settings 2.png

Avatar

Level 3

Thanks AndyKent, appreciate your help! very helpful! 

Avatar

Community Advisor

If you're talking about holidays that your whole company has off, Workfront refers to these as "exceptions". You can use these directions to set them. https://experienceleague.adobe.com/docs/workfront/using/administration-and-setup/set-up-wf/configure... 

 

See also, https://experienceleague.adobe.com/docs/workfront/using/administration-and-setup/set-up-wf/configure... 

Avatar

Level 3

See you again, you are the expert! Really appreciate it, thank you very much!

Avatar

Level 3

I am working with system admin team to fix it.