Expand my Community achievements bar.

Latest Community Ideas Review is Out: Discover What’s New and What to Expect!

Adding "Cancel Task" Status for tasks no longer required

Avatar

Level 1

I ran into this document where on page 4, as a solution 2, 

Troubleshooting_Manage+a+project.pdf (workfront.com)

Solution 2
If a task is no longer needed, set the status to Cancelled rather than deleting the task.Deleting the task removes it from the project timeline, which ultimately affects the project’s planned dates and, possibly, the completion date.For example, if a task for “Review the design” was slated for 3 days and that is deleted from the project plan, then everything else in the project moves 3 days earlier.By cancelling the task, you’re simply saying “not going to do that one” and the timeline stays the same.

 

I have looked under settings and I do not have the option to create a "Cancel" task. I can create a task but only have three options "New, In Progress, and Complete".

Pragash_0-1673970834572.png

How can we create an option to set a task to be canceled?

 

 

3 Replies

Avatar

Community Advisor

Ultimately CANCEL status will equate with something, most reasonable is COMPLETE. We have set it up like this:

Rafal_Bainie_0-1674034429996.png

 

Avatar

Level 1

Have you noticed that when you cancel all child tasks, the parent task automatically becomes "Complete" not cancelled?

Pragash_0-1674060386038.png

 

Avatar

Community Advisor

I can see this being "per design", but worth checking with the support