Expand my Community achievements bar.

Join us LIVE in San Francisco on November 14th for Experience Makers The Skill Exchange. Don't miss out on this free learning event!

Resource Planner - Exclude Planned hours on Cancelled Tasks

Avatar

Level 5

10/10/19

I'm noticing that tasks with planned hours that have been CANCELLED are falsely inflating workloads in the capacity planner. When a task is cancelled, the hours should not impact capacity reporting as the work is cancelled.


Currently the only work around I know of is to delete the planned hours from each task. This is a huge effort as the PM has to go into EACH task & wipe out the planned hours & duration to effectively remove the time.


SUGGESTION: automate the deletion of planned hours from cancelled tasks or figure out a way to exclude those hours from being counted in capacity & resourcing tools.

1 Comment

Avatar

Level 2

12/6/19

Agreed. This is absolutely vital when looking at role level data, completed tasks should not show as requiring future capacity. It can lead to wildly inaccurate capacity projections