Resource Planner - Exclude Planned hours on Cancelled Tasks

  • October 10, 2019
  • 1 reply
  • 412 views

I'm noticing that tasks with planned hours that have been CANCELLED are falsely inflating workloads in the capacity planner. When a task is cancelled, the hours should not impact capacity reporting as the work is cancelled.


Currently the only work around I know of is to delete the planned hours from each task. This is a huge effort as the PM has to go into EACH task & wipe out the planned hours & duration to effectively remove the time.


SUGGESTION: automate the deletion of planned hours from cancelled tasks or figure out a way to exclude those hours from being counted in capacity & resourcing tools.

1 reply

Level 2
December 6, 2019

Agreed. This is absolutely vital when looking at role level data, completed tasks should not show as requiring future capacity. It can lead to wildly inaccurate capacity projections