Expand my Community achievements bar.

Auto update predecessors when adding a new task

Avatar

Level 2

1/2/18

I have a large project with hundreds of tasks and predecessars defined.

I need to add a new task in the beginning part of the project.

The problem, this changes all the task numbers, but the predecessors do not automatically update accordingly. HELP! I’d prefer not to have to go through and review and update all predecessors manually!

1 Comment

Avatar

Level 10

1/2/18

Hi - actually if you refresh the page or go to Project Actions -> Recalculate Timeline, the predecessors do update. I've had several people call me about this before. I'd love it though if they would update right away to save some people from having heart attacks. ;)