Advanced reporting against baselines

Avatar

Level 6

3/10/17

Would like the ability to layer in historical data of project types against current project reports so you can view current project performance against historic.

Would want to be able to see this at the task role level - compare hours by task role on this project against historical usage

This would be beneficial to compare - portfolio performance against a specific project type, as well as whole company performance against a specific project type

1 Comment

Avatar

Community Advisor

3/10/17

Hi Ryan. As a workaround, we use a bar chart grouped by Task Name and compare the average Template Task duration against the average actual duration, as below. Perhaps that will give you some ideas.