Updating task planned hour through fusion issue

Avatar

Level 1


It is not updating the task planned hour


Rohith8_0-1766464557530.png

 

Rohith8_2-1766464758346.png

 

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Level 7

Try updating the variable "Work" Instead.

Lawson02_0-1767227790464.png


Also make sure that planned hours does not say "This field is automatically calculated by the system". If the latter happens you may have to change the duration type as that has an effect on locking certain aspects so that the system calculates it. I would read about duration type before messing with it because some changes are irreversible in templates.

Lawson02_1-1767227811830.png

 

View solution in original post

3 Replies

Avatar

Correct answer by
Level 7

Try updating the variable "Work" Instead.

Lawson02_0-1767227790464.png


Also make sure that planned hours does not say "This field is automatically calculated by the system". If the latter happens you may have to change the duration type as that has an effect on locking certain aspects so that the system calculates it. I would read about duration type before messing with it because some changes are irreversible in templates.

Lawson02_1-1767227811830.png

 

Avatar

Level 1

@Lawson02 
Bro, could you please tell me why the fusion  through planned hour field it is not updating?
And when we are using "work" to update.The task duration is not updated automatically.

Avatar

Level 7

Try updating all of these except for task constraint. Play around with these as the locked variables change different aspects of how duration is calculated via hours. I have had trouble with Duration and Planned Hours in the past, they are very frustrating to work with. Submitting a support ticket is a solid way to fix these problems and clear any confusion.

Lawson02_0-1767632834068.png