Expand my Community achievements bar.

Don’t miss the Workfront AMA: System Smarts & Strategic Starts! Ask your questions about keeping Workfront running smoothly, planning enhancements, reporting, or adoption, and get practical insights from Adobe experts.
SOLVED

Remove Commit Date

Avatar

Level 3

Anyone been able to figure out how to remove/delete/change commit dates using Fusion. WF has/had an annoying habit of setting the commit date to the planned CPL date when a user self-assigns themselves to a task and it's PITA to clean up.......

1 Accepted Solution

Avatar

Correct answer by
Level 2

You can't set it to 'null,' but you can replace it with another date. If you set it to null, it'll just keep the original commit date. 

View solution in original post

1 Reply

Avatar

Correct answer by
Level 2

You can't set it to 'null,' but you can replace it with another date. If you set it to null, it'll just keep the original commit date.