How to get below highlighted date from the iterator bundle output?

Avatar

Level 1

How to get below highlighted date from the iterator bundle output?

 

Screenshot 2025-03-03 190502.png

 

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Hi @Sethu_AnandR 

here is one way -

SveniX_0-1741019833042.png

 

but I'd suggest not using a value you need as a key... So I would modify the scenario upstream so you end up with eg 

  • Bundle X
    • date: 2025-02....
    • value: 480

View solution in original post

2 Replies

Avatar

Correct answer by
Community Advisor

Hi @Sethu_AnandR 

here is one way -

SveniX_0-1741019833042.png

 

but I'd suggest not using a value you need as a key... So I would modify the scenario upstream so you end up with eg 

  • Bundle X
    • date: 2025-02....
    • value: 480