I created a New Template and my template durations are not rolling up correctly. I have task constraint set to 'As Soon as Possible'. See attached. I can't figure out why the durations do not roll up to total duration. I have tried everything.
Topics help categorize Community content and increase your ability to discover relevant content.
Views
Replies
Total Likes
I don't see that you've attached anything so feel free to try that part again.
Views
Replies
Total Likes
Hi Skyehansen, thank you for bringing this to my attention I have attached the screenshot.
Views
Replies
Total Likes
Views
Replies
Total Likes
Can you expand to show all 26 tasks? My feeling is that they aren't adding up because you don't have ENOUGH predecessors linking tasks from one end of the project to the other. By seeing all 26, we can maybe recommend some tasks that you can link to show the continuity of the project timeline.
@AlexJones954 Just checking in! Were you able to get this resolved? If you found your own solution, sharing the details would be a big help to others who might face the same issue later on. And if one of the replies here helped, whether it fully solved the problem or simply pointed you in the right direction, marking it as accepted makes it much easier for future readers to find. Thanks again for helping close the loop and contributing to the community!