I am trying to pull a report that is showing us the difference (excluding weekends & holidays) from when a request is submitted (Request > Entry Date) to when one of our specific tasks within the Resolve Project is marked as complete (task name = Send to Requestor for Approval).
Essentially we're trying to track the turn times from request submission to the delivery to the requestor - however we have additional tasks that follow our "Send to Requestor for Approval" task that we do not want to account for so the project's Actual Completion Date would not work for us, it will need to be that particular task.
Any help is appreciated