Attached is the Task Kickstart I used to import. setCategoryID is in Column 'EX.' I may have just uploaded the custom form, and not the actual parameter answers I wanted to populate the form with.
Thanks Skye! Looks like the Custom form attached. I couldn't get the answer (Parameter Option) to populate though. Any ideas there? I appreciate your insight!
Hello, Wondering if this capability exists/is possible. Prerequisite information:I have a Control Project that will house ~400 Tasks. For context, but not relevant to this problem, I will use this project as an external lookup to populate a custom field's answers on a separate form. I have a Custom...
Here is some information to hopefully outline this scenario:No Fusion is used, but can be suggested as a solution if there is none available in Core Workfront.Compliance Request Project - Standalone Queue Project that teammates can access and add an issue by going to the Request queueWebdev Pjt Temp...
Hello, I have a Project report with the following groupings:However, our org would like to enable custom quarters with the following dates: However, keeping the same groupings leads to 'No Value' when using custom values. Any workarounds for this?
Thank you for your response, Manish! I've added that filter and I think it's a step in the right direction; however, now it is only tracking "Summary" which is the top-level parent task, technically. It is also duplicating it in the report:
Hello, I've built a report that captures a project's Parent tasks' planned duration. While the report does capture the Parent task's name and planned duration, I want a summation of all the subtasks' planned duration; instead, I get a duplicate line item named with the parent task. Filters: The Re...