Hi everyone!
I don't know if this has been posted before or if this is the right place to post, but I was wondering if there was a reason why users aren't able to input/edit their Actual Hours on the Project Timeline. You are able to directly adjust Planned Hours on this view simply by clicking ov...
Hi there!
Our company works with a third-party team in a different timezone. Whenever the project manager of that team assigns one of those members to a task, the task dates automatically adjust to the following day. We don't seem to have any issues like this when assigning tasks to users in our co...