My team was just discussing the same, but slightly different, issue last
week. The only other reference to this was from 2016, so thank you Chris
Project Preferences - Typical hours worked=8, typical days worked=5. So
when we give a task a 5-day duration, we notice it's calculating from
8am the first day until 12pm the fifth day and starting the next task at
12pm same day. It wasn't allocating a full work day, so it was
shortening our timeline. Timeline based on Simple Calculation. It
appears I'...