Expand my Community achievements bar.

KristenS_WF
KristenS_WF
Offline
Type
  • All
  • Questions
  • Discussions
  • Ideas
  • Blogs
Filter by user contributions
  • That is weird.  I tried a fresh report, and your solution worked.  Maybe there was some artifact/glitch in my original report causing trouble.   Thanks!  

    Type

    Questions

    Views

    1.0K

    Likes

    0

    Replies

    0
  • Ah... figured it out.  I saw that Parent > Milestone ID was an available field in the report, so I modified its Text Mode to the following:   displayname= linkedname=parent namekey=view.relatedcolumn namekeyargkey.0=parent namekeyargkey.1=milestone namekeyargkey.2=name querysort=parent:milestone:nam...

    Type

    Questions

    Views

    1.0K

    Like

    1

    Replies

    2
  • I've tried both valuefield=parent:milestone:name and valueexpression={parent}.{milestone}.{name}, but neither gives a result.   I'm not sure what I'm doing wrong.  

    Type

    Questions

    Views

    1.0K

    Likes

    0

    Replies

    0
  • Is there a way to display, in a Task report, the milestone name for the task's parent task?   I've been playing around with Text Mode (and looking at the API Explorer) but can't seem to get my syntax right.   Thanks.

    Type

    Questions

    Views

    1.0K

    Likes

    0

    Replies

    5
  • Ah... got in touch with Customer Service.   Using the 'Planned Hours' field doesn't work (and its system/API name--'workRequired'--isn't an option).   Had to use 'Work' instead.

    Type

    Questions

    Views

    1.2K

    Likes

    4

    Replies

    3
  • All,   We have around 350+ current projects launched from a new workflow this year.  We recently pulled data for one task in the workflow (1st copyedit) and discovered that the actual hours entered for completed tasks is significantly lower than the task's planned hours in the template.  We want to ...

    Type

    Questions

    Views

    1.2K

    Likes

    0

    Replies

    4
  • Hi All,   Thanks for the suggestions--I'll play around with them.   Just for more info, here's what I'm using now.  Columns A-E and G show info from the back-end projects (column F is a calculated column in the report).  Column H is info from the predecessor projects using collections.  It's kind of...

    Type

    Questions

    Views

    1.1K

    Likes

    0

    Replies

    0
  • Thanks, Chris!  This is very helpful.  

    Type

    Questions

    Views

    1.7K

    Like

    1

    Replies

    0
  • Is it possible to update task predecessors through Fusion?  I just kick-started a group of 30+ projects, and I need to add cross-project predecessors to a specific task in each project.   When assigning predecessors last year (prior to us having Fusion access), I created a task report and pasted in ...

    Type

    Questions

    Views

    1.7K

    Like

    1

    Replies

    6
  • Hi all,   We have a suite of products that are broken into two basic project types--front-end content module projects (kind of similar to chapters of a book) and back-end for-sale deliverable projects.  The back-end deliverables are linked to their constituent modules through the use of cross-projec...

    Type

    Questions

    Views

    1.2K

    Like

    1

    Replies

    6
Top badges earned by KristenS_WF
Customize the badges you want to showcase on your profile