would it be possible to backup workflow for continue process on a new server ?

Avatar

Avatar

kachainn7521991

Avatar

kachainn7521991

kachainn7521991

09-02-2016

Example my workflow is running and not finish  but I need to move workflow to a new server now.


would it be possible  my workflow move to continue left step on a new server by continue from the old process ?

Accepted Solutions (1)

Accepted Solutions (1)

Avatar

Avatar

WASIL

Employee

Avatar

WASIL

Employee

WASIL
Employee

11-02-2016

Export the database and import it to the database which is used by new server, that way it might retain step. Also, makes sure to use same GDS.

Thanks,

Wasil

Answers (1)

Answers (1)

Avatar

Avatar

kachainn7521991

Avatar

kachainn7521991

kachainn7521991

15-02-2016

Thank you WASIL