How to check if batch segmentation evaluation job ran successfully?

Avatar

Level 7

Hi there,

 

I recently updated the batch segmentation evaluation job time, so wanted to double check if it ran successfully and how long it took. Is there a way to verify this?

 

Thanks,

 

1 Accepted Solution

Avatar

Correct answer by
Level 7

Hello,

 

Looking into the UI, I found that you can actually see if it ran successfully through the "Monitoring" tab --> Audience --> Segmentation jobs.

 

 

View solution in original post

2 Replies

Avatar

Level 3

Hey,

Earlier in the UI AEP used to show the schedule and last evaluation time, with new UI updates, I don't happen to see it anymore.

 

I would call the below API to get me the recent evaluation job to check the status:

 

https://platform.adobe.io/data/core/ups/segment/jobs?limit=1&sort=creationTime:desc

 

Thanks!

Avatar

Correct answer by
Level 7

Hello,

 

Looking into the UI, I found that you can actually see if it ran successfully through the "Monitoring" tab --> Audience --> Segmentation jobs.