Hi Team,
What is the best and easy way to sync the content in stage with prod.
since size of the content is huge can't go with manual package manager.
Is there any other way we can achieve this from?
Thanks
Ganesh
+91-9380201140
These two have the same solutions .
https://dgtljourney.wordpress.com/2017/04/05/content-synchronization/
https://medium.com/globant/aem-content-synchronization-cb1e15b0c3f8
I want to try RECAP (VLT-sync) but not getting proper document on how to install it and run it.
@aem-enthu27 what kind of AEM install you are following? On-Premise, AMS, AEM cloud?
AEM as a cloud
You can write a scheduler that will run at a specific time and will sync the content between prod and stage. we are following the same way.
what is the logic you will write inside scheduler ? replication from prod to stage author and publish ?
Who mark comments as Coreect answer
Hi @aem-enthu27 ,
Currently there is no automated way to sync the content between different instances of cloud. The only option right now available is using package manager. There is a roadmap to have content sync feature by end of this year. But unfortunately, we don't have anything as of now.
Hello @aem-enthu27
Please refer to the following option for content sync:
https://adobe-consulting-services.github.io/acs-aem-commons/features/contentsync/index.html
It can sync between any environments
On Adobe Cloud Manager Content Sync option is coming, where you can sync content either under sites or dam from Prod to Stage.