How to Edit scheduled projects in workspace

Avatar

Level 5

I have checked under Analytics > Components > Scheduled Projects, But in the Scheduled Projects Manager I am not able to edit my scheduled project to add new mail id's to delivery list. Is there any option to edit scheduled workspace project?

1 Accepted Solution

Avatar

Correct answer by
Level 5

In Analytics > Components > Scheduled Projects, if you click on the blue title of the project, you should be able to edit the scheduled project to add new recipients. There is no Edit button, you just click on the title.

Reference: Scheduled Projects

View solution in original post

1 Reply

Avatar

Correct answer by
Level 5

In Analytics > Components > Scheduled Projects, if you click on the blue title of the project, you should be able to edit the scheduled project to add new recipients. There is no Edit button, you just click on the title.

Reference: Scheduled Projects