Yet another question! I'm finding that with cross-.. | Community
Skip to main content
Level 2
February 3, 2021
Question

Yet another question! I'm finding that with cross-..

  • February 3, 2021
  • 1 reply
  • 522 views

Yet another question! I'm finding that with cross-project predecessors, "update on change" does not automatically change (recalculate) successor task dates when dates on the predecessor tasks are changed. One has to manually recalculate the timeline or wait overnight. I want to be that this is working as intended. If so, I'm going to submit an idea that it be made so.

Thanks!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

Doug_Den_Hoed__AtAppStore
Community Advisor
Community Advisor
February 3, 2021

Hi Jason,

Yep, As Designed, as I understand it; one of several reasons we created our Force Timeline solution, which provides a simple, schedulable way to automatically recalculate the timelines for all projects matching a selected filter, ensuring they are up to date.

Regards,

Doug

JasonLe4Author
Level 2
February 4, 2021

Ok, that's what I figured. Thanks for your help Doug!