Question
Yet another question! I'm finding that with cross-..
Yet another question! I'm finding that with cross-project predecessors, "update on change" does not automatically change (recalculate) successor task dates when dates on the predecessor tasks are changed. One has to manually recalculate the timeline or wait overnight. I want to be that this is working as intended. If so, I'm going to submit an idea that it be made so.
Thanks!