Workload balancer and planned hours for tasks with multiple users assigned

Avatar

Level 2

When multiple resources are assigned to a particular task, how do you ensure accurate planned hours are rolling up into the workload balancer for each resource for that task?

Thank you!

 

 

1 Reply

Avatar

Community Advisor

you can define this in Advanced allocations/assignments:

Rafal_Bainie_0-1728571381102.png

you define Planned Hours per resource:

Rafal_Bainie_1-1728571442480.png

this window is also available from Workload balancer view, hold CTRL and click on the task and select advanced as above