We use a "My Active Assignments" report, for users to track tasks which are ready for them to begin.
We've noticed recently that some tasks with cross-project predecessors are not
showing on the report, even though the cross-project predecessor task is complete.
The filter on the My Active Assignments report is:
assignedToID=$$USER.ID
assignedToID_Mod=in
project:status=DED ONH PLN QUE BLG
project:status_Mod=notin
status=AD AA
status_Mod=in
task:canStart=true
task:canStart_Mod=eq
task:status=CPL
task:status_Mod=notin
I’ve spot checked projects with cross-project predecessors, and some users are seeing the task on their My Active Assignments report, while others are not.
What else do I need to consider that may be affecting this?
Topics help categorize Community content and increase your ability to discover relevant content.
Views
Replies
Total Likes
I ran into a similar problem, and it was tasks assigned to multiple individuals.
When a task is assigned to multiple people, the "assignedToID" is the first person listed. It doesn't care about person 2, 3, 4, etc. only the "primary assignee".
I switched my reports to "Assignment Users ID", and that pulled all tasks a person was assigned to regardless of whether they were first, second, etc.
Something worth checking.
Views
Replies
Total Likes