Your achievements

Level 1

0% to

Level 2

Tip /
Sign in

Sign in to Community

to gain points, level up, and earn exciting badges like the new
Bedrock Mission!

Learn more

View all

Sign in to view all badges

Why are some tasks with cross-project predecessors not showing up on My Active Assignments report?

Avatar

Level 4

We use a "My Active Assignments" report, for users to track tasks which are ready for them to begin.

We've noticed recently that some tasks with cross-project predecessors are not

showing on the report, even though the cross-project predecessor task is complete.

The filter on the My Active Assignments report is:

assignedToID=$$USER.ID

assignedToID_Mod=in

project:status=DED ONH PLN QUE BLG

project:status_Mod=notin

status=AD AA

status_Mod=in

task:canStart=true

task:canStart_Mod=eq

task:status=CPL

task:status_Mod=notin

I’ve spot checked projects with cross-project predecessors, and some users are seeing the task on their My Active Assignments report, while others are not.

What else do I need to consider that may be affecting this?

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

0 Replies

Avatar

Level 4

I ran into a similar problem, and it was tasks assigned to multiple individuals.

When a task is assigned to multiple people, the "assignedToID" is the first person listed. It doesn't care about person 2, 3, 4, etc. only the "primary assignee".

I switched my reports to "Assignment Users ID", and that pulled all tasks a person was assigned to regardless of whether they were first, second, etc.

Something worth checking.