Hello again everyone, I wanted to provide another update, as I know this issue has been a hot topic for many people. First, I want to reiterate there are 2 workarounds: 1) You can set the resource leveling to automatic. -- This just means that if a single user is assigned to multiple tasks that are scheduled to be worked on all at the same time on that project , the resource leveling will re-align the dates so they don't conflict. This only happens for tasks that have 1 assignee, and it's the same assignee on each task on that one project. 2) You can inline add your tasks, refresh the page, then add your predecessor relationships, IF you choose to stick with manual resource leveling. **Note : Per @Doug Den Hoed and his example screenshot above, you can bulk edit the resource leveling option in Workfront. At this point, we've had enough info to review this issue, and based on the possible workarounds and how it's functioned for several years, we've already created a story to address this issue long term, and are aiming to include it with the new task functionality with 2019.1. Note, that is not set in stone, but is something that we're aiming for. Keep an eye on our "https://workfront.com/release" title="Workfront Release">Workfront Release page for up to date information on the features we will be including on the upcoming release. Please don't hesitate to reach out to Workfront support if you have any questions, or direct message me on the community, and I will reply as I get time. Thank you everyone! Dustin Martin Assigned Support Engineer Workfront