We are looking for a report to identify how our users are doing on completing tasks on time over time.

Is there a way to track by individual the number of tasks they complete late over a given period of time (weekly, monthly, etc)?

 

Currently I am able to see the number of 'current' late tasks by user, but we are looking for a more historical view over time as it occurred vs just as of today.

 

Is there a report that exists to identify this information, or have you created something similar?

Any help or direction will be appreciated.

 

Thank you!
Tammy

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

2 Replies

Avatar

Level 6

Hi @TammyCa1 
You could run task report or an assignment report - if those tasks can have multiple users, you likely want the assignment report. 

You can then group by user. 

As a filter you compare actual vs planned completion date: 

Task report

actualCompletionDate=FIELD:plannedCompletionDate
actualCompletionDate_Mod=gt

Assignment report

task:actualCompletionDate=FIELD:task:plannedCompletionDate
task:actualCompletionDate_Mod=gt

 

Avatar

Community Advisor

 

Hi @TammyCa1,

 

For some inspiration, the "Coffee Is For Closers" Task Report I just whipped up below is:

  • filtered to return only those Tasks whose Actual Completion Date is NOT blank
  • grouped by Actual Completion Date (to the week), by Last Updated By Name
  • charted in columns by week, by Last Updated By Name
  • prompted by Actual Completion Date, by Last Updated By Name
  • defaults to showing the chart

 

Have fun!

 

Regards,

Doug

 