Hi again, I'm trying to create a calculated column difference of Actual (difference of Actual Start to Completion) to the Template duration. So far I have the following in text mode which is not working for me: valueexpression=(WEEKDAYDIFF({actualStartDate},{actualCompletionDate}))-({template:durationMinutes}) I was able to achieve the difference for Actual to Planned with the following: valueexpression=(WEEKDAYDIFF({actualStartDate},{actualCompletionDate}))-(WEEKDAYDIFF({plannedStartDate},{plannedCompletionDate})) Is this possible at the project level? TIA, Ruby Ruby Aran Investors Group/ Mackenzie Investments
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

2 Replies

Avatar

Level 8
It's syntax. When you put the {} braces around expressions for valueexpression, you seperate them with }.{ not : So it should be: valueexpression=(WEEKDAYDIFF({actualStartDate},{actualCompletionDate}))-({template}.{durationMinutes}) Barry Buchanan - WMA Work Management Australia

Avatar

Level 3
Thanks for letting me know, Barry. That worked perfectly! Ruby Aran Mackenzie Investments