Expand my Community achievements bar.

Don’t miss the Workfront AMA: System Smarts & Strategic Starts! Ask your questions about keeping Workfront running smoothly, planning enhancements, reporting, or adoption, and get practical insights from Adobe experts.

Mark Solution

This conversation has been locked due to inactivity. Please create a new post.

SOLVED

Task report with chart of task completed prior to the completion date compared to past the completion date

Avatar

Level 3

Any ideas on how to set up a simple report using a chart option of either the number or percentage of tasks completed by the planned completion date compared to those completed after the planned completion date.  I can't seem to set the report up correctly to get the data I want on a chart.  Thanks!

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

 

Hi @SuzyF,

 

I suggest you group by Task Progress (e.g. On Time, At Risk, Behind, Late), then chart as you see fit (e.g. Pie Chart, Stacked Column over time, etc.) .

 

Regards,

Doug

View solution in original post

1 Reply

Avatar

Correct answer by
Community Advisor

 

Hi @SuzyF,

 

I suggest you group by Task Progress (e.g. On Time, At Risk, Behind, Late), then chart as you see fit (e.g. Pie Chart, Stacked Column over time, etc.) .

 

Regards,

Doug