Any ideas on how to set up a simple report using a chart option of either the number or percentage of tasks completed by the planned completion date compared to those completed after the planned completion date. I can't seem to set the report up correctly to get the data I want on a chart. Thanks!
Solved! Go to Solution.
Hi @SuzyF,
I suggest you group by Task Progress (e.g. On Time, At Risk, Behind, Late), then chart as you see fit (e.g. Pie Chart, Stacked Column over time, etc.) .
Regards,
Doug
TIP: if this solved your problem, I invite you to consider marking it as a Correct Answer to help others who might also find it of use
Views
Replies
Total Likes
Hi @SuzyF,
I suggest you group by Task Progress (e.g. On Time, At Risk, Behind, Late), then chart as you see fit (e.g. Pie Chart, Stacked Column over time, etc.) .
Regards,
Doug
TIP: if this solved your problem, I invite you to consider marking it as a Correct Answer to help others who might also find it of use
Views
Replies
Total Likes