Expand my Community achievements bar.

Join us LIVE in San Francisco on November 14th for Experience Makers The Skill Exchange. Don't miss out on this free learning event!

Task Percent Complete

Avatar

Level 4
Hello! Is there a setting on the task level to show the gradual task percent completion as users mark Done with My Part. For example: John, David, Jane, and Sue are all on one task together. John and Sue both mark Done with My Part, but David and Jane have not. Is there a way for that task to automatically show itself as 50% complete when seeing the complete task list at the project level? Right now, our tasks are either 0% or 100%, so we can't tell if anyone has even clicked the button without clicking into each individual task to see. Would be great if there were an automated setting we could apply. Thank you, Lila Whitney Discover Financial Services
7 Replies

Avatar

Level 10
Hi Lila, I don't believe so. The % Complete field at the individual Task level is very manual. The only way I can think of to accomplish this (other than some kind of API or app from Doug) would be to have a separate task for each person under a Parent or Summary Task. Then when they mark each task complete, it'll roll up the calculation of the % Complete of the Parent/Summary Task.

Avatar

Community Advisor
Huh! Why, thanks Vic. Interesting thought. I'll let it marinate a bit. Lila, you might also be interested in my "http://store.atappstore.com/2010/09/going-the-extra-milestone/">Going The Extra Milestone blog post, which explains a (crazy, tricky, but out of the box) technique that might give you what you need. Regards, Doug Doug Den Hoed - AtAppStore Got Skills? Lend a hand! https://community.workfront.com/participate/unanswered-threads

Avatar

Level 10
How do you know I meant you? ��

Avatar

Level 10
Hi Vic, you can add a collection to the view that shows "Done with my part" statuses. https:// wf-pro .com/textmode/text-mode-views-collections/#done-statuses

Avatar

Level 4
This worked well for me! Thanks, Narayan! Lila Whitney | Discover Brand Creative Group 2500 Lake Cook Road, Riverwoods, IL 60015 P: 224.405.5857 E: lila whitney@discover.com

Avatar

Level 10
Oh great! I didn't realize it was you who first asked.

Avatar

Community Advisor
Touche, Vic üòâ Having slept on it...I remember designing an "http://store.atappstore.com/product/ubercalc/">UberCalc solution that: Would use a filter to retrieve those Tasks with a custom data parameter called Auto-Complete and had a Percent Complete less than 100 For each, calculate the ideal Percent Complete at the time using the Planned Start Date and Planned Completion Dates vs $$NOW (ie assuming the Task was happening on time, in real time) Update each Task's Percent Complete accordingly Would also recalc such Task's Project's timelines Effectively auto-advance Workfront Projects, in a "no hands" fasion Would pair beautfully with our "http://store.atappstore.com/product/executive-status-report/">Executive Status Report solution Sorry, Other Doug Vic Meant, if I stole your thunder. Regards, Doug Doug Den Hoed - AtAppStore Got Skills? Lend a hand! https://community.workfront.com/participate/unanswered-threads