Expand my Community achievements bar.

Don’t miss the Workfront AMA: System Smarts & Strategic Starts! Ask your questions about keeping Workfront running smoothly, planning enhancements, reporting, or adoption, and get practical insights from Adobe experts.

Mark Solution

This conversation has been locked due to inactivity. Please create a new post.

SOLVED

Task-Level field inherit default value from Parent-Level field.

Avatar

Level 6

I have a few Radio Button (Yes/No) fields that exist at the project-level on a custom form. The same fields exist at the Task-Level on a different custom form. Not all tasks have this custom form, only tasks where it's relevant.

My question is, Is it possible to make the task-level values default to the project-level values of that same field?

Example, there may be a field that states "Compliance Required?" at the project-level, to indicate if the Project needs to be reviewed by Compliance. If the value is set to "Y", I'd want all instances of the task-level "Compliance Required?" field to inherit the value of "Y". Users should be able to adjust the task-level value if specific tasks do not need Compliance.

I thought maybe I could do this with a calculated field, but then I'm not sure my users would be able to change the task-level value from it's default "inherited" value (e.g. change the "Y" to an "N" at the task-level) if Compliance isn't needed on that specific task.

1 Accepted Solution

Avatar

Correct answer by
Community Advisor


Hi @J_Mas,

 

No, but if you default the (same) radio buttons to nothing, you could think of the Task level one as an Override to the Project level one by having a Task level calculated parameter consider both (eg IF(ISBLANK({radio}),{project}.{radio},{radio}))

 

regards,

Doug

 

 

View solution in original post

1 Reply

Avatar

Correct answer by
Community Advisor


Hi @J_Mas,

 

No, but if you default the (same) radio buttons to nothing, you could think of the Task level one as an Override to the Project level one by having a Task level calculated parameter consider both (eg IF(ISBLANK({radio}),{project}.{radio},{radio}))

 

regards,

Doug