Expand my Community achievements bar.

Latest Community Ideas Review is Out: Discover What’s New and What to Expect!

Projects are often stuck on the last same 3 tasks (needed for admin purposes) and it is clogging up all the reports we are creating - How can we exclude them?

Avatar

Level 1

Hi all,

 

All of our templates (and therefore projects) are finishing with the same 3 tasks. These tasks are there for admin reasons but the teams in charge of them are always taking a very long time to complete them despite our efforts.

 

Because of the delays of these 3 admin tasks, the Project reports are now very busy with projects stuck on these tasks which makes them harder to read.

In a project report, how could I exclude Projects where the "up-next" tasks is one of these admin tasks. These tasks have the exact same names on all templates.

 

thanks,

Alexandra 

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

3 Replies

Avatar

Level 6

Hi @Alexandra2 

 

Here's how you could do this: 

  1. make a parent task for those last 3 admin tasks, eg. "Admin Tasks". It completes when all 3 children are complete.
  2. Note the name of the task whose completion signals "project is complete", e.g. the task just before the "Admin Tasks" parent.
    Ideally this is a parent task that encapsulates all tasks outside the admin tasks. Let's assume this task is called "Project Execution". It completes when all its children are complete. 
  3. Select text-mode, and add
EXISTS:a:$$EXISTSMOD=NOTEXISTS
EXISTS:a:$$OBJCODE=TASK
EXISTS:a:projectID=FIELD:ID

EXISTS:a:name=Admin Tasks
EXISTS:a:status=CPL
EXISTS:a:status_Mod=cine

EXISTS:a:name=Project Execution
EXISTS:a:status=CPL

 

This equates to 

  • all projects where
  • we do not have tasks that (NOTEXISTS)
  • a task named Admin Tasks is not complete and
  • a task named Project Execution is complete 

Avatar

Level 1

Thanks a lot for these tips - I will do a few tests - thanks again

Avatar

Community Advisor

 

Hi @Alexandra2,

 

For these often left incomplete 3 Admin Tasks that are cluttering your project reports (and skewing your stats to Late, etc.), consider

 

  • creating a new "Admin Leftovers" project (either one big one, or one for each such project, suffixed as such), then
  • move the 3 Admin Tasks to the Leftovers project

 

By doing so, you'll clear up the clutter, and focus a spotlight on the Leftovers in a way that might help get things moving again.

 

If so, bonus; if not, it might also be time to delete those 3 Admin Tasks from the Template...

 

Regards,

Doug