Hi: 1. Can you confirm what the scheduled hours column should be calculating? è The Scheduled Hours should be the hours in the current forecast - the project plan; è The Budgeted Hours should be the hours in the labor budget. This number is visible and adjusted in the capacity planner. The Resource Estimate screen in the Business Case will show the PM the difference between the labor being allotted to the project (budgeted hours) and the labor being requested (current forecast in the project plan); è When you select Set Budget to Schedule in the Resource Estimates screen, the budget number will be the same as the current forecast in the report; è When PMs adjust the project plan, you will have to go back and set budget to schedule. I also find it interesting to look at the differences between the budget (last current forecast) and the current forecast. WorkFront highlights differences in red. It tells me what kind of resource changes the PM is making. But I digress… è I set budget to schedule in the Resource Estimate screen, then I ran the report I had built. Note that Budgeted and Scheduled hours are identical: [cid:image002.jpg@01D1CC5B.684222B0] 2. Did you build from a resource estimate type report? è Yes, I started with a Resource Estimate report. è I tried to get a Kick Start of the report, so I could just email you the text mode code, but I can’t get this report to appear in the KickStart Export screen. Not sure why. [cid:image008.jpg@01D1CC5B.684222B0] [cid:image009.jpg@01D1CC5B.684222B0] 3. Do you have any additional settings in your columns? è Nope. Building the report took less than a minute. The default Resource Estimate report has these four attributes: Alloc. Date, Bud. Hours, Sch. Hour, and ObjId. I add Job Role: Name and delete ObjID. I summarize the Sch. Hours attribute by SUM; è Then I create a Matrix Grouping, group the row on Resource Estimate >> Allocation Date and then group the column on Job Role >> Name; è For the Row Grouping, I group dates by Week and Show weeks with no data: [cid:image010.jpg@01D1CC5B.684222B0] è On my screen, after I select Group Dates by Week, it doesn’t show up on the screen, its blank, but I know it’s there: [cid:image011.jpg@01D1CC5B.684222B0] è I open the Matrix Settings and deselect Show Record Counts and Deselect Show Value Column. [cid:image012.jpg@01D1CC5B.684222B0] è That’s it. Send me a screen shot of your fields and what the resulting report looks like… 4. Is your Matrix showing FTE total value or something different? If FTE, how did you achieve this? è The Matrix report shows the sum of all scheduled hours for a given week (row) for each role (column). I’m not calculating FTE, it’s just straight hours in this report. Having said that, do you want FTE? I haven’t used FTE in a labor utilization calculation, but it’s do-able. Let me know how it goes! Eric