Multiple Critical Paths in Workfront

Avatar

Level 1
We recently switched from MPS to Workfront. We are in the Pharmaceutical Development arena doing multiple long tasks ect. Has anyone found away to carry multiple critical path in WF. Margaret Duffy Sarepta
2 Replies

Avatar

Level 10
Hi Margaret, There is an isCritical attribute in the API on Tasks into which I'm doing a bit more research, but "https://community.workfront.com/discussions/community-home/digestviewer/viewthread?MessageKey=ebb9d895-1c7d-4080-af01-0566279ea9a2&CommunityKey=aaafaff0-5e4e-4e38-8903-f1f990935567&tab=digestviewer#bmebb9d895-1c7d-4080-af01-0566279ea9a2">this thread also has some information you might find useful. Regards, Doug Doug Den Hoed - AtAppStore Got Skills? Lend a hand! https://community.workfront.com/participate/unanswered-threads

Avatar

Level 10
Bit more research complete, Margret: by filtering tasks to Is Critical = True (and optionally, showing the Gantt chart with the Critical Path option turned on), Workfront then shows only the critical tasks. Regards, Doug Doug Den Hoed - AtAppStore Got Skills? Lend a hand! https://community.workfront.com/participate/unanswered-threads