Hello Workfront Community, I've been able to import a MS Project (2016) XML file into Workfront. The MS Project field titled "WBS" doesn't synchronize the proper numbers with the Workfront-Task field titled "Work Breakdown Structure". The first MS Project column titled 'WBS', starts the first row numbering at 100. This number scheme of starting at 100 will help determine where the sub-tasks could manually be indented...i.e. 101,102,103 etc.. will be indented under 100. The issue occurs during the import when the Workfront-Task "Work Breakdown Structure" displays the first number as "1". Is there a better way to import from MS Project (2016) and retain a field that identies a custom number? Thanks in advance! Kind regards, - Joe